Gunite Construction

The Gunite Construction Process
The process of building your swimming pool environment begins with a preconstruction meeting with your project manager. During this meeting pool location and elevations will be finalized. Any questions you might have regarding the construction process will be addressed.

1. Pool construction typically begins 1-3 weeks after permits are issued.

2. It typically takes 6-8 weeks from excavation of the pool to completion.

3. Extensive masonry work and landscaping can extend projects beyond 6 – 8 weeks

  1. Preconstruction

Preconstruction includes finalizing the design, securing the building permit, and making sure the site has been properly prepared. Tree removal, if needed, should be completed before excavation begins and all underground sprinkler systems should be shut down. If there are any obstructions regarding access such as fences or landscaping it should be addressed at this time. Lang Pools can help facilitate if necessary.

 

  1. Excavation

The fun begins. A large excavator will be delivered to your site the night prior to excavation or the morning of. If materials are being removed from the site tri axel trucks will also be on site. Typically, excavation can be completed within 1-2 days.

  1. Framing

Once the pool has been excavated we begin to install the forms. Using 2 x 4 and 1 x 4 lumber we form your pool shape. This form dictates the concrete shell “bond beam” elevation and is the guide for all things to come.

  1. Steel Tex and Pool Interior Plumbing

Once the framing is complete we install a steel re-enforced waterproof membrane. This helps stabilize the excavated pool area and provides a secure backing for the concrete. We also install any plumbing that will be encased in concrete within the pool shell. Skimmers, main drains, return and vacuum lines are installed at this time and pressure tested.

 

  1. Steel Framework

Next, the steel reinforcing framework is installed. Our steel designs are approved by a licensed engineer before this step begins. We install #4 (1/2” rebar) which is larger than industry standard #3(3/8”) that most competitors use. This is also the time we take care of the electrical bonding or grounding of the steel skeleton.

  1. Concrete Shell

Next, and perhaps the most exciting step, is the application of the concrete. Also known as shotcrete or gunite, the concrete is pneumatically applied by trained professionals. It’s exciting to watch as your new pool starts to take shape. This is also when we will build your steps in the shallow end, any loveseats or benches, and any other custom features. Typically we allow 14 days for our pool shells to cure before applying plaster. Other phases of construction will occur during the curing process.

  1. Electrical Wiring and Pool Equipment Plumbing

Next, we complete the electrical work and plumbing of the pool equipment. All equipment is placed on the finished concrete equipment pad and tied into the pool plumbing that was stubbed out of the concrete shell. All pool plumbing is once again pressure tested. If needed, an electrical panel is installed. Then all lights, pumps, heaters, switches, special features and control systems will be connected to the circuit breakers. (Depending on site conditions this stage can occur earlier in the construction process.)

  1. Backfill

Once the concrete shell is completed we allow it to cure for a minimum of 3-5 days, then we return to remove all the wood forms and to backfill the voids surrounding the pool shell. This “rough grade” will level the terrain surrounding the pool and make way for you masonry work to begin.

  1. Tile Installation

Next the six inch band of decorative tile is installed and grouted. Any decorative floor tiles, step markers or bench markers are also installed at this time.

  1. Deck Installation

Whether it’s bluestone set in cement, stamped concrete, decorative pavers or any of our other beautiful deck materials; you will begin to see the culmination of all the talented individuals who have been working on your site. This is truly when you begin to see your pool environment come together. Typically natural stone and decorative paver products take 2-4 weeks to install and poured concrete products can be completed within a week.

  1. Applying the Interior Finish

The pool interior is hand-troweled white or colored plaster. Or, it may be one of the stunning new aggregate finishes such as Wet Edge Technology, River Rok or Diamond Brite. Typically this process is completed in 4-6 hours and then the pool is filled with water immediately. The water helps to cure the interior finish.

 

  1. Pool Start Up

Finally, it is time for your pools start-up and pool school. One of our service professionals will schedule a time to meet with you at your new pool. At that time, they will explain all of the operations and functions of the pool and answer any questions you might have. After that, the only thing left is for you to start swimming and enjoy your new Lang Pool!